What are curtailment payments?
A generator is curtailed when it is instructed, or chooses, to produce less than the wind or sun would allow. A curtailment payment, also called a constraint payment or a deemed generation payment, makes up some or all of the income lost. Whether one is due depends on the cause.
| Cause of curtailment | Typical compensation | Who pays |
|---|---|---|
| Grid congestion or system stability: the system operator instructs a reduction | Varies by country: full, partial above a threshold, or none | System operator, funded through network charges |
| Balancing: the operator accepts the generator's offer to reduce output | The price the generator bid | System operator |
| The buyer cannot or will not take the power | Deemed generation at the contract price | The buyer under the power purchase agreement |
| Negative prices: the generator switches off by choice, or a subsidy stops paying | None | Nobody |
| Outage of the generator's own equipment or connection | None, unless insured | Insurer, if covered |
Rules differ widely. In Great Britain's balancing mechanism, generators submit the prices at which they are willing to reduce output, and the operator pays those it accepts. Other markets compensate grid-related curtailment by law, and some pay nothing below an annual number of hours. The accounting starts from the contract or rule that creates the right to be paid.
Curtailment payments: which standard applies?
| Source of the payment | Generator's accounting | Presented as |
|---|---|---|
| Deemed generation clause in a PPA that is a revenue contract | IFRS 15: variable consideration under the PPA, recognised for the period of curtailment, limited to the amount highly probable not to reverse | Revenue from contracts with customers |
| Deemed generation clause in a PPA that contains a lease | IFRS 16: a variable lease payment, recognised as income when earned | Lease income |
| System operator pays an accepted bid to reduce output | IFRS 15: a balancing service supplied to the operator | Revenue, often a balancing or ancillary services line |
| Compensation set by law or grid code, paid by the operator | A policy choice applied consistently: IFRS 15 revenue if it arises from the connection and market arrangements with the operator, otherwise other operating income | Revenue or other operating income |
| Compensation funded by a government | IAS 20: a grant related to income, recognised when there is reasonable assurance it will be received | Other income, or deducted from the related cost |
| Settlement formula in a virtual PPA that uses possible output | IFRS 9: part of the derivative's cash flows | Derivative gains and losses, or the hedged line |
| Business interruption insurance | IAS 37: recognised when recovery is virtually certain | Other income |
| No compensation | No entry | Revenue is lower |
The first row is the most common for farms with long-term contracts. A PPA with a deemed generation clause is close in substance to an availability arrangement: the buyer pays for the farm being ready to generate, whether or not the power is taken. See power purchase agreements and capacity payments.
Worked example: a wind farm with a deemed generation clause
A wind farm sells all its output under a PPA at US$ 60 a MWh. The PPA is a revenue contract, not a lease. If the grid operator curtails the farm, the buyer pays the contract price for the energy that would have been generated, except for the first 2,000 MWh each year, which the farm bears. Curtailment the farm chooses itself is not compensated.
| Year | MWh | US$ thousand at 60 |
|---|---|---|
| Possible output from the wind | 150,000 | 9,000 |
| Grid curtailment | (9,000) | |
| Switched off during negative prices | (3,000) | |
| Delivered and sold | 138,000 | 8,280 |
| Grid curtailment above the 2,000 MWh threshold: deemed generation | 7,000 | 420 |
| Revenue recognised | 8,700 | |
| Output lost with no compensation | 5,000 | 300 |
Deemed output cannot be read from a meter. It is calculated from wind speeds measured at the turbines and each turbine's power curve, and the two sides often disagree. Suppose the farm's own calculation gives 7,600 MWh of compensated curtailment and the buyer has so far agreed 7,000. The extra 600 MWh, US$ 36 thousand, is variable consideration that is not yet highly probable, so it is left out of revenue until it is agreed.
What are the journal entries?
| Event | Entry | US$ thousand |
|---|---|---|
| Electricity delivered in the year | Dr Trade receivable Cr Revenue: electricity | 8,280 8,280 |
| Deemed generation agreed with the buyer | Dr Trade receivable Cr Revenue: deemed generation | 420 420 |
| Disputed 600 MWh, later agreed | Dr Trade receivable Cr Revenue: deemed generation | 36 36 |
| If the PPA were a lease | Dr Receivable Cr Lease income: variable lease payments | 420 420 |
| If the operator, not the buyer, paid under an accepted bid | Dr Receivable from system operator Cr Revenue: balancing services | Amount of the bid |
Compensation measured at the contract price already replaces the revenue lost. Where a farm also loses subsidy income or renewable energy certificates for the curtailed hours, the compensation formula sometimes includes those, and the amount is split between the lines it replaces. See feed-in tariffs and subsidies and renewable energy certificates.
Is a curtailment payment revenue or other income?
Ask three questions in order.
- Is the payer a customer? The buyer under a PPA is. A system operator that pays for a reduction it requested is buying a balancing service, and supplying that service is part of a generator's ordinary activities. Both are revenue from contracts with customers.
- Is the payer a government, or passing on government money? Then the payment is a government grant, presented as other income or set against the cost it compensates.
- Neither? A right created by statute with no contract behind it is not clearly inside IFRS 15. Most generators still present it in revenue, on the grounds that it replaces sales of electricity; others use other operating income. Either is acceptable if the policy is disclosed and applied consistently.
Under IFRS 18 the category is not in doubt: whichever line is used, the amount belongs to the operating category, because it arises from the farm's main business. See the IFRS 18 categories.
How does the buyer account for deemed generation payments?
A buyer that pays for power it did not receive records the payment as a cost of electricity in the period of the curtailment. It gets nothing to carry forward, so there is no asset. If the PPA contains a lease, the payment is a variable lease payment, expensed when the curtailment happens and left out of the lease liability. Under a virtual PPA settled on possible output, the payment is simply part of the derivative's settlement.
What else does curtailment affect?
- Impairment. A sustained rise in uncompensated curtailment is an indicator of impairment under IAS 36. Cash flow forecasts should use an explicit curtailment assumption for each year, and the compensation rules that will then apply, not an average of the past. See IAS 36 impairment.
- Contract valuations. The fair value of a virtual PPA or another derivative on the farm's output uses expected volume after curtailment.
- Hedges. A farm that has sold a fixed volume forward and is then curtailed is over-hedged. The excess is ineffectiveness, or the hedged sales are no longer highly probable.
- Depreciation. Straight-line depreciation is unaffected. A units-of-production method would charge less in a curtailed year, which is one reason it is rarely used for wind and solar. See wind and solar asset lives.
- Storage. A battery added to a site to store curtailed output is a separate asset with its own revenue streams. See battery storage projects.
- Disclosure. The policy for curtailment compensation, the judgement on disputed volumes, and compensation shown as its own category in the revenue note if it is material.
How much is one point of curtailment worth?
It is worth working out, because the number is larger than it looks. For the farm in the example, one percentage point of uncompensated curtailment is 1,500 MWh a year, or US$ 90,000 of revenue at the contract price, with almost no cost saved, since wind has no fuel bill. Over a remaining life of 20 years, discounted at 7%, that is 90,000 × 10.594 = US$ 953,461 of value in use. A forecast that assumes 3% curtailment where 8% is now normal overstates the recoverable amount by about US$ 4.8 million. See value in use.
How does US GAAP differ?
The analysis runs the same way: ASC 606 for payments from a customer, with the variable consideration constraint set at probable instead of highly probable, and ASC 842 for PPAs that are leases. Two differences matter. US GAAP has no general standard on government grants for businesses before ASU 2025-10 takes effect, so statutory compensation has usually been accounted for by analogy. And a PPA that is a derivative under ASC 815 may qualify for the normal purchases and normal sales exception, in which case deemed generation is accounted for as revenue on an accrual basis. See IAS 20 vs US GAAP and power and utilities accounting.
Keep going
Our free Excel models work through the examples in these guides, and the comparisons show where IFRS and US GAAP part ways. Every guide names the Chartered Accountant who wrote it and the one who reviewed it.
Questions people ask
What is a curtailment payment?
Compensation paid to a generator, usually a wind or solar farm, for electricity it could have produced but did not because it was instructed to reduce output.
Are curtailment payments revenue under IFRS 15?
Yes when they come from a customer: the buyer under a power purchase agreement, or a system operator paying for a requested reduction. Compensation set only by law is revenue or other income by policy.
What is deemed generation?
The output a wind or solar farm would have produced during a curtailment, calculated from measured wind or sunlight. Many power purchase agreements pay the contract price for it.
When is disputed curtailment compensation recognised?
Only to the extent that it is highly probable a significant reversal will not occur, which usually means when the volume is agreed with the payer.
Is uncompensated curtailment an expense?
No. There is no entry: revenue is simply lower. A lasting increase in uncompensated curtailment is an impairment indicator for the plant.
How does the buyer account for deemed generation payments?
As a cost of electricity in the period of curtailment, or as a variable lease payment if the agreement contains a lease.
Sources
The standards, updates and other documents this guide draws on.
- IFRS Foundation: IFRS 15 Revenue from Contracts with Customers
- IFRS Foundation: IFRS 16 Leases
- IFRS Foundation: IAS 20 Accounting for Government Grants and Disclosure of Government Assistance
- IFRS Foundation: IAS 36 Impairment of Assets
Rules and fees change. If you are reading this long after November 19, 2026, confirm the figures with the source before you rely on them.
Related guides
More in Power and renewables
This guide is general information. It is not tax or legal advice for your situation.