Loss-making construction contracts: an example
A contractor agreed to build a bridge for a fixed price of CU 10 million. Steel prices have risen, and it now expects total costs of 10.6 million: 9.8 million of incremental costs, such as materials, subcontractors and site labour, and 0.8 million of other costs directly related to the contract, such as depreciation of its cranes used on site. Costs incurred to date are 4.24 million.
| CU million | Amount |
|---|---|
| Progress: 4.24 / 10.6 | 40% |
| Revenue recognised: 40% x 10 | 4.00 |
| Costs incurred | (4.24) |
| Loss on work done | (0.24) |
| Onerous provision for work to do: remaining costs 6.36 less remaining revenue 6.00 | (0.36) |
| Total loss recognised this year | (0.60) |
The whole expected loss of 0.6 million is recognised now. As the remaining work is done, the provision is used: each year's costs exceed the revenue recognised, and the provision release offsets the difference, so later years show no further loss unless estimates worsen again.
How does the loss fall year by year?
Suppose estimates do not change again. By the end of year 2 costs to date are 7.95 million (75% complete), and the bridge is finished in year 3.
| CU million | Year 1 | Year 2 | Year 3 | Total |
|---|---|---|---|---|
| Revenue | 4.00 | 3.50 | 2.50 | 10.00 |
| Contract costs | (4.24) | (3.71) | (2.65) | (10.60) |
| Onerous provision: charge (release) | (0.36) | 0.21 | 0.15 | 0.00 |
| Profit (loss) | (0.60) | 0.00 | 0.00 | (0.60) |
| Provision at year end | 0.36 | 0.15 | 0.00 |
What are the journal entries?
| When | Entry | CU million |
|---|---|---|
| Year 1: recognise the onerous provision | Dr Contract costs: onerous contract (profit or loss) Cr Provision for onerous contracts | 0.36 |
| Year 2: use part of the provision as the work is done | Dr Provision for onerous contracts Cr Contract costs (profit or loss) | 0.21 |
| Year 3: use the rest on completion | Dr Provision for onerous contracts Cr Contract costs (profit or loss) | 0.15 |
Revenue and the actual costs are booked in the usual way; the provision entries only move the loss on future work into the year it became expected. If estimates worsen again, the extra loss is recognised at once in the same two parts: a catch-up through progress on work done, and a top-up of the provision for work still to do.
Which costs count as costs of fulfilling a contract?
Since the 2022 amendment to IAS 37, the costs of fulfilling a contract include both the incremental costs, such as direct labour and materials, and an allocation of other costs that relate directly to fulfilling contracts, such as depreciation of equipment used on the contract and site management. General and administrative costs are excluded unless explicitly chargeable to the client. Including the allocated costs makes more contracts onerous than an incremental-only view would.
What if exiting the contract is cheaper?
The unavoidable cost is the lower of the cost of fulfilling the contract and any compensation or penalty from failing to fulfil it. Where a contractor could terminate by paying a fixed penalty smaller than the expected loss, the provision is limited to that penalty, though in practice contractors rarely have such a right.
What is tested before the provision?
Assets dedicated to the contract, such as capitalised mobilisation costs or contract assets, are tested for impairment first, and the onerous provision covers only the loss that remains. Capitalised contract costs are impaired when their carrying amount exceeds the remaining consideration less the costs still to be incurred.
At what level is the test applied?
Contract by contract, after combining contracts that were negotiated as a package. A profitable contract with the same client cannot offset a loss-making one unless the two are combined under IFRS 15.
What do contractors disclose about loss-making contracts?
The onerous contract provisions and their movements, the main estimates behind them, and, where significant, the contracts or portfolios concerned. Large losses on a few contracts often explain a contractor's results, so readers look for them.
How does US GAAP treat loss contracts?
US GAAP kept specific guidance in ASC 605-35: when a construction contract is expected to make a loss, the whole loss is provided for in the period it becomes evident, with similar results. See IAS 37 onerous contracts, the cost-to-cost method and construction accounting.
Keep going
Our free Excel models work through the examples in these guides, and the comparisons show where IFRS and US GAAP part ways. Every guide names the Chartered Accountant who wrote it and the one who reviewed it.
Questions people ask
How are loss-making construction contracts accounted for?
The loss on work done is recognised through IFRS 15 progress, and the remaining expected loss is provided for at once as an onerous contract under IAS 37.
Which costs are included in an onerous contract test?
Since 2022, incremental costs plus an allocation of other costs directly related to fulfilling the contract, such as depreciation of equipment used on it.
When is the loss on a construction contract recognised?
As soon as it becomes expected, not spread over the remaining work.
How does US GAAP treat loss-making construction contracts?
ASC 605-35 requires the whole expected loss to be provided for when it becomes evident.
Sources
The standards, updates and other documents this guide draws on.
- IFRS Foundation: IFRS 15 Revenue from Contracts with Customers
- IFRS Foundation: IAS 37 Provisions, Contingent Liabilities and Contingent Assets
Rules and fees change. If you are reading this long after November 12, 2026, confirm the figures with the source before you rely on them.
Related guides
More in Construction
This guide is general information. It is not tax or legal advice for your situation.