Cost-to-cost method formula
Percentage of completion = costs incurred to date / total estimated contract costs. Cumulative revenue = percentage of completion x transaction price. Revenue for the period = cumulative revenue less revenue recognised in earlier periods. Total estimated costs are costs to date plus the current estimate of costs to complete, so the percentage is re-measured every reporting date, and any change in the estimate is caught up in the current period rather than spread forward.
Cost-to-cost method example
A contractor signs a 12,000 fixed-price contract and first estimates total costs at 9,600. During the second year it revises the estimate to 10,000 because steel prices rise. Costs to date are 2,400 at the end of year 1, 6,000 at the end of year 2 and 10,000 on completion.
| CU | Year 1 | Year 2 | Year 3 |
|---|---|---|---|
| Costs to date | 2,400 | 6,000 | 10,000 |
| Estimated total cost | 9,600 | 10,000 | 10,000 |
| Percentage complete | 25% | 60% | 100% |
| Cumulative revenue (12,000 x %) | 3,000 | 7,200 | 12,000 |
| Revenue for the year | 3,000 | 4,200 | 4,800 |
| Costs for the year | 2,400 | 3,600 | 4,000 |
| Profit for the year | 600 | 600 | 800 |
Year 2 shows the catch-up. Had the estimate stayed at 9,600, 6,000 of costs would have meant 62.5% complete and cumulative revenue of 7,500. The higher estimate cuts progress to 60% and cumulative revenue to 7,200, and the whole difference lands in year 2's revenue. The three years add up to the contract's total profit of 2,000.
Is the cost-to-cost method an input method?
Yes. IFRS 15 and ASC 606 describe two families of method for measuring progress. Output methods look at what has been delivered: units completed, milestones reached, surveys of work performed. Input methods look at what has been put in: hours, machine time or, most often, costs. Cost-to-cost is the usual input method because contractors already track costs by job, and it is acceptable only when costs are a reasonable proxy for the work transferred. When they are not, the costs that distort the picture are stripped out, which is what the next section is about.
Costs to leave out: uninstalled materials and wasted costs
Two adjustments come up on almost every large contract. First, significant materials delivered to the site but not yet installed, when the customer controls them, the item is not distinct, its cost is significant and the contractor did not design or make it: revenue equal to their cost is recognised when control passes, with no margin, and the cost is excluded from the progress measure. Second, wasted materials, labour and rework that were not priced into the contract are expensed and excluded, because a mistake is not progress. Other costs to leave out are general overheads not attributable to the contract and pre-contract or mobilisation costs that transfer nothing to the client; see mobilisation and tender costs.
An example. A contractor builds an office block for CU 10 million, with total expected costs of 8 million, including lifts costing 1.6 million bought from a specialist supplier. At the year end, costs incurred are 4.2 million. They include the lifts, delivered to site and controlled by the client but not yet installed, and 0.2 million of rework after the contractor poured a floor slab incorrectly.
| CU million | Unadjusted | Adjusted under IFRS 15 |
|---|---|---|
| Costs counted towards progress | 4.2 | 4.2 - 1.6 lifts - 0.2 rework = 2.4 |
| Total expected costs used | 8.0 | 8.0 - 1.6 lifts = 6.4 |
| Progress | 52.5% | 37.5% |
| Revenue | 5.25 | 0.375 x 8.4 + 1.6 lifts at cost = 4.75 |
| Costs expensed | 4.2 | 4.2 |
| Profit | 1.05 | 0.55 |
Counting the lifts' cost as progress would treat the contractor as half finished when it has done well under half the building work, and the rework would make a mistake look like progress. The adjusted figure recognises the lifts at cost, with their margin earned when they are installed, and expenses the rework without counting it. Materials still in the contractor's own stores are inventory and are not counted at all.
Cost-to-cost method journal entries
Using year 1 of the three-year example, with 2,400 of costs paid in cash and 2,400 billed to the customer during the year:
| Entry | Debit | Credit |
|---|---|---|
| Costs incurred on the contract | Contract costs (cost of sales) 2,400 | Cash or payables 2,400 |
| Progress billing to the customer | Trade receivable 2,400 | Contract liability (billings) 2,400 |
| Revenue at 25% complete | Contract liability 2,400 and contract asset 600 | Revenue 3,000 |
Revenue of 3,000 exceeds billings of 2,400, so the 600 not yet billed is a contract asset. If billings run ahead of revenue, the excess stays as a contract liability. Uninstalled materials under the first example are a separate entry: debit contract asset or receivable and credit revenue for their cost when the customer takes control, with the same amount in cost of sales. See contract assets and liabilities on construction contracts.
How are costs to complete estimated?
From a bottom-up forecast of remaining work: subcontracts let and to be let, materials, labour, plant, site overheads, risks and contingencies, updated every period by the project team and reviewed by finance. Subcontract costs count when the subcontractor's work is done, usually as it is certified, not when the subcontract is signed or an advance is paid. A rise in costs to complete lowers progress to date as well as the expected margin, and both effects are caught up in the current period, as year 2 of the example shows. If the revised estimate turns the contract loss-making, the whole expected loss is provided for at once. Optimistic cost-to-complete estimates are one of the most common sources of contractor losses that appear suddenly.
Cost-to-cost under IFRS 15 vs ASC 606
The method is the same under both standards, because the two were written together: the same formula, the same treatment of uninstalled materials and wasted costs, and the same rule that a change in estimate is a cumulative catch-up. US readers will meet older labels, "percentage of completion" and "completed contract", from the pre-2018 construction guidance; the completed contract method no longer exists, and revenue is recognised over time only when one of the three over-time criteria is met. Both standards also let a contractor that cannot yet measure progress reasonably, but expects to recover its costs, recognise revenue equal to costs incurred until it can. See IFRS 15 vs ASC 606 for the few differences in the standards as a whole.
When is an output method better?
When costs do not track the work transferred, for example a contract with very uneven material costs, or a programme of identical houses where units completed are a clearer measure. Surveys of work performed, valued by a quantity surveyor, are a common output method in construction. Whichever method is chosen, it is applied consistently to similar contracts. See construction revenue over time and construction accounting.
Keep going
Our free Excel models work through the examples in these guides, and the comparisons show where IFRS and US GAAP part ways. Every guide names the Chartered Accountant who wrote it and the one who reviewed it.
Questions people ask
What is the cost-to-cost method?
An input method for recognising revenue over time: progress equals costs incurred to date divided by total estimated costs, and that percentage of the contract price is recognised as cumulative revenue. It is the usual method on construction and engineering contracts under IFRS 15 and ASC 606.
Is cost-to-cost an input or output method?
An input method. It measures the resources put into the contract, in this case costs, rather than what has been delivered. Output methods, such as units completed or surveys of work performed, measure the result instead.
How do you calculate percentage of completion with cost-to-cost?
Divide the costs incurred to date by the total estimated costs of the contract, which are costs to date plus the current estimate of costs to complete. Leave out costs that do not reflect work transferred, such as uninstalled materials and rework. Multiply the percentage by the transaction price to get cumulative revenue.
What happens when estimated total costs change?
The percentage of completion is recalculated with the new total, and the difference between the new cumulative revenue and what was recognised before goes through the current period: a cumulative catch-up, not a prospective spread. If the contract becomes loss-making, the full expected loss is recognised immediately.
Sources
The standards, updates and other documents this guide draws on.
- IFRS Foundation: IFRS 15 Revenue from Contracts with Customers
- FASB Accounting Standards Codification: Topic 606, Revenue from Contracts with Customers
- Financial Accounting Standards Board: Revenue recognition
Rules and fees change. If you are reading this long after October 30, 2026, confirm the figures with the source before you rely on them.
Related guides
More in Construction
This guide is general information. It is not tax or legal advice for your situation.