The cost-to-cost method on construction contracts: an example
A contractor builds an office block for CU 10 million, with total expected costs of 8 million, including lifts costing 1.6 million bought from a specialist supplier. At the year end, costs incurred are 4.2 million. They include the lifts, delivered to site and controlled by the client but not yet installed, and 0.2 million of rework after the contractor poured a floor slab incorrectly.
| CU million | Unadjusted | Adjusted under IFRS 15 |
|---|---|---|
| Costs counted towards progress | 4.2 | 4.2 - 1.6 lifts - 0.2 rework = 2.4 |
| Total expected costs used | 8.0 | 8.0 - 1.6 lifts = 6.4 |
| Progress | 52.5% | 37.5% |
| Revenue | 5.25 | 0.375 x 8.4 + 1.6 lifts at cost = 4.75 |
| Costs expensed | 4.2 | 4.2 |
| Profit | 1.05 | 0.55 |
Counting the lifts' cost as progress would treat the contractor as half finished when it has done well under half the building work, and the rework would make a mistake look like progress. The adjusted figure recognises the lifts at cost, with their margin earned when they are installed, and expenses the rework without counting it.
When are uninstalled materials recognised at cost?
IFRS 15 sets the conditions: the item is not distinct, the client obtains control of it before it is installed, its cost is significant relative to the total expected costs, and the contractor obtains it from a supplier without being significantly involved in designing or making it. Revenue equal to its cost is then recognised when control passes. Materials still in the contractor's stores are inventory and not counted at all.
Which other costs are excluded?
- Wasted materials, labour or other resources from inefficiencies that were not reflected in the contract price, such as rework of defective work.
- Costs that do not relate to the contract, such as general overheads not directly attributable to it.
- Pre-contract and mobilisation costs that do not transfer anything to the client; see mobilisation and tender costs.
How do subcontractor costs fit in?
Subcontract costs count when the subcontractor's work is done, usually as it is certified, not when the subcontract is signed or an advance is paid. An advance paid to a subcontractor is a prepayment until the related work is performed, so it does not count towards progress until the subcontractor actually does the work.
How are costs to complete estimated?
From a bottom-up forecast of remaining work: subcontracts let and to be let, materials, labour, plant, site overheads, risks and contingencies, updated every period by the project team and reviewed by finance. A rise in costs to complete lowers progress to date as well as the expected margin, and both effects are caught up in the current period. Optimistic cost-to-complete estimates are one of the most common sources of contractor losses that appear suddenly.
When is an output method better?
When costs do not track the work transferred, for example a contract with very uneven material costs, or a programme of identical houses where units completed are a clearer measure. Surveys of work performed, valued by a quantity surveyor, are a common output method in construction. Whichever method is chosen, it is applied consistently to similar contracts. See construction revenue over time and construction accounting.
Need help applying the standards?
Our Chartered Accountants help finance teams and students apply IFRS and US GAAP to real transactions.
Questions people ask
What is the cost-to-cost method?
An input method that measures progress as costs incurred to date divided by total expected costs, applied to the contract price to recognise revenue.
How are uninstalled materials treated under the cost-to-cost method?
When they meet IFRS 15's conditions, they are excluded from progress and revenue equal to their cost is recognised, with no margin, when the client controls them.
Are inefficiency costs included in progress?
No. Wasted materials, labour and rework not reflected in the price are expensed and excluded from the measure of progress.
When should an output method be used instead?
When costs do not track the work transferred, such as contracts with uneven material costs or programmes of identical units.
Sources
Every fee, date and rule on this page was taken from these official and primary sources.
Rules and fees change. If you are reading this long after October 7, 2026, confirm the figures with the source before you rely on them.
Related guides
More in Construction
This guide is general information. It is not tax or legal advice for your situation.